Project Scope Management

 

PMBOK Guide

葉明導讀

 

Project Scope Management

l          專案範疇管理要求對專案的範疇做精準的掌控,過與不及都算是不成功的管理。 Project Scope Statement 和 WBS 二大重點,必須充份的加以了解。

n          To ensure that the project includes all work required, and only the work required

n          Processes include:

1.          Scope Planning

2.          Scope Definition

3.          Create WBS

4.          Scope Verification

5.          Scope Control

 


 

Scope Planning

l          訂出範疇管理計畫,做為範疇管理的依據。

n          Creates a project scope management plan that documents how the project scope will be defined, verified, controlled, and how the work breakdown structure will be created and defined

n          Planning Process Group

 


 

Scope Definition

l          訂出詳盡專案範疇說明書,以利專案的持繼進行。

n          Develops a detailed project scope statement as the basis for future project decision

n          Planning Process Group

 

Stakeholder Analysis

l          分析利害關係,是定義範疇時不缺的一項以確保範疇能滿足所需

n          Identifies the influence and interests of the various stakeholders

n          Documents their needs, wants, and expectations

n          To turn stakeholder needs, wants, and expectations into requirements

n          A tool of Scope Definition

 

Project Scope Statement

l          專案範疇說明書明確界定出專案的範疇,是所有利害關係人對範疇的認知依據。

n          Describes, in detail, the project's deliverables and the work required to create those deliverables

n          Provides a common understanding of the project scope among all project stakeholders and describes the project's major objectives

n          A output of Scope definition

n          Includes:

l          Project objectives

l          Product scope description

l          Project requirements

l          Project boundaries

l          Project deliverables

l          Product acceptance criteria

l          Project constrains

l          Project assumptions

l          Initial project organization

l          Initial defined risks

l          Schedule milestones

l          Fund limitation

l          Cost estimate

l          Project configuration management requirements

l          Project specifications

l          Approval requirements

 

Objective

l          目標必須要能量測,要能量必須要能量化。

n          Should be measurable

n          With attribute, metric, value

 


Create WBS

l          訂出 WBS (Work Breakdown Structure)以落實對專案範疇 的掌控,並有利於後繼的 Schedule 製作。

n          Subdivides the major project deliverables and project work into smaller, more manageable components

n          Planning Process Group

 

WBS

l          作分解結是專案管理最重要的觀念之一,也是專案管理的核心技術, 它的觀念並不困難,實務上卻需要相當經驗的累積。

n          A deliverable-oriented hierarchical decomposition of the work

n          Organizes and defines the total scope of the project

n          Subdivides the project work into smaller, more manageable pieces of work

n          Prevents work from slipping through the cracks

n          The process of creating a WBS results in Team buy-in

n          Decompose work until it has a meaningful conclusion

n          Decompose work until it cannot be logically subdivided further

n          Decompose work until it can be realistically estimated

n          As an effective aid for Stakeholder communications

n          Used for communicating with the customer

n          Every item should have a unique identifier

n          Each level of a WBS provides progressively greater detail

 

Work Package

l          工作包是 WBS 的最終層級已足可估算成本及時程

n          The lowest-level component in the WBS

n          The point at which the cost and schedule for the work can be reliable estimated

 

WBS Dictionary

l          WBS 各單項的用以避免對工作內容的差異

n          Includes a code of account identifier, a statement of work, responsible organization, and a list of schedule milestones

n          To make sure the team clearly knows what work is included in each of their tasks

n          Documents contains detailed description of work packages

n          A output of Create WBS

 

Scope Baseline

l          專案管理的 Baseline 有三Scope Baseline, Time Baseline, Cost Baseline

n          A output of Create WBS

n          Includes:

1.          Project Scope Statement

2.          WBS

3.          WBS dictionary

 


 

Scope Verification

l          對交付物是否符合範疇規定的驗證

n          Formalizes acceptance of the completed project deliverables

n          Customer acceptance of project effort

n          Concerned with acceptance of the deliverables

n          Be done at the end of each phase of the project

n          Before moving to the next phase

n          Monitoring & Controlling Process Group

 

Inspection

l          Inspection 也是 Perform Quality Control 的工具以一。

n          The tool of Scope Verification

n          Variously called reviews, product reviews, audits, and walkthrough

 


 

Scope Control

l          "There are three certainties in life: taxes, death, and changes to project scope." 範疇變更無可避免,但需嚴加管制以減少對專案造成衝

n          Controls changes to the project scope

n          Concerned with influencing the factors that create project scope changes and controlling of those changes

n          Monitoring & Controlling Process Group

 

 

 

 

 