Project Time Management

 

PMBOK Guide

葉明導讀

 

Project Time management

l          專案時間管理是專案管理中最旗幟鮮明的領域, 其中的甘特圖 (Gantt Chart) 已然成了專案管理的圖騰。時程 (Schedule) 的制定完成,是專完案計畫階段的重大里程碑,而時程管制 (Schedule Control) 則是專案執行階段最重要的工作之一。

n          To accomplish timely completion of the project

n          Process include

1.          Activity Definition

2.          Activity Sequencing

3.          Activity Resource Estimating

4.          Activity Duration Estimating

5.          Schedule Development

6.          Schedule Control

 


 

Activity Definition

l          活動定義是將工作包 (Work package) 再予以分解成為活動 (Activity)。工作包代表交付物的層級,活動則是工作項目的層級,用以產出交付物。

n          Identifies the specific schedule activities that need to be performed to produce the various project deliverables

n          Decompose work package into smaller components call schedule activities

n          Planning Process Group

 


 

Activity Sequencing

l          活動排序就是把各項活動的依存間係,用網狀圖來表現,重點在於產出網狀圖的各種知識及技術。

n          Identifies and documents dependencies among schedule activities

n          Creates project schedule network diagram

n          Planning Process Group

n          Tools and Techniques

l          Precedence Diagramming Method (PDM)

l          Arrow Diagramming Method (ADM)

l          Dependency Determination

l          Applying Leads and lags

 

 Logical Relationship

l          或稱 Precedence relationship / dependency, 指兩活動間的相互依存關係,並可搭配 Lead / Lag 的條件使用。

n          Includes

l          FS : Finish-to-Start

l          FF : Finish-to-Finish

l          SS : Start-to-Start

l          SF : Start-to-Finish

 

Precedence Diagramming Method (PDM)

l          優先順序圖示法是一種網狀圖 的表示方法用節點來表示活動

n          A tool of Activity Sequencing

n          Also called activity-on-node (AON)

n          Uses boxes or rectangles (nodes) to represent activities

n          Use arrows to show dependencies

n          Includes FS, FF, SS, SF

 

Arrow Diagramming Method (ADM)

l          箭號圖示法是一種網狀圖 的表示方法,用箭號來表示活動。

n          A tool of Activity Sequencing

n          Also called activity-on-arrow (AOA)

n          Uses arrows to present activities

n          Connects activities at nodes to show their dependencies

n          Uses only FS

n          Dummy activities could be required

n          Duration of a dummy activity is zero

 

Dependency

l          依存關係即邏輯關係,另一種分類方式如下所述

n          Types include

l          Mandatory dependency: hard logic, the nature of work

l          Discretionary dependency: preferred logic, preferential logic or soft logic,

l          External dependency: between project activities and non-project activities

 

Lead

l          活動間的依存關係不會剛好都是FS / FF / SS / SF, 可能允許提前 (Lead),或是必須延後 (Lag)。

n          A modification of a logical relationship that an acceleration of the successor activity

 

Lag

l          不要把 Lag 當作 Delay 或是 Reserve, 這些都是極大的誤解。

n          A modification of a logical relationship that directs a delay in the successor activity

n          Waiting time

 

Project Schedule Network Diagram

l          這個階段的網狀圖只有顯示活動間的依存關係, 並不包含各活動的工期。網狀圖職埸上常被稱為 PERT 圖,與 PERT 的原意不盡相同,須注意曲分。

n          Schematic displays of the project schedule activities and the logical relationship among them

n          A output of Activity Sequencing

 

 


 

Activity Resource Estimating

l          活動工期的長短,與投入資源的型式及多寡有關,故須先進行資源估算。 專案管理的估算流程,另有 Activity Duration Estimating 及 Cost Estimating

n          Estimates the type and quantities of resources required to perform each schedule activity

n          Planning Process Group

n          Tools and Techniques include

l          Expert Judgment

l          Alternative analysis

l          Published estimating data

l          Project management software

l          Bottom-up estimating

 


 

Activity Duration Estimating

l          估算各項活動的工期,以便進行 Schedule 制訂。

n          Estimates the number of work periods that will be needed to complete individual schedule activities

n          Planning Process Group

n          Tools and Techniques include

l          Expert judgment

l          Analogous estimating

l          Parametric estimating

l          Three-Point estimating

l          Reserve analysis

 

 Analogous Estimating

l          類比估算 需快速成本低是其優點較不精確是其缺點

n          Also called top-down estimating

n          A form of expert judgment

n          Uses historical information

 

Three-Point Estimates

l          PERT採用這種估算方式,是對單一估算 值的一種改進,以提高估算的精確 度

n          Most likely, Optimistic, Pessimistic

n          PERT estimate: (P+4M+O)/6

n          PERT Standard deviation: (P-O)/6

 


 

Schedule Development

l          專案時間管理在計劃階段的終極目標便是制訂專案時程。繁 複的工具及技術, 都是為了能規劃出合理可行的時程,做為執行及監控專案工作的依據。

n          Analyzes activity sequences, durations, resource requirements, and schedule constraints to create the project schedule

n          Planning Process Group

n          Tools and Techniques include

l          Schedule Network Analysis

l          Critical Path Method

l          Schedule Compression

l          What-If Scenario Analysis

l          Resource Leveling

l          Critical Chain Method

l          Project Management Software

l          Applying Calendars

l          Adjusting Leads and Lags

l          Schedule Model

 

 Critical Path Method (CPM)

l          要徑法規劃專案時程的必備技術及知識,是 由美國杜邦公司發展出來的

n          The longest duration through a network diagram

n          The shortest time to complete the project

n          Forward pass: calculates the early start and finish dates for all schedule activities.

n          Backward pass: calculates the late stare and finish dates for all schedule activities

n          Critical paths have either a zero or negative total float

n          A critical path can run over a dummy

n          There can be more than one critical path

n          More critical paths increase the project risk

 

Float

l          浮時要徑法最在意的掌控元素

n          Also called slack

n          Calculated using the CPM

n          Provides the schedule flexibility

n          Free float: the amount of time that a schedule activity can be delayed without delay the early start of any immediately successor schedule activity

n          Total float: the total amount of time that a schedule activity may be delay from its early start without delaying the project finish date

 

Schedule Compression

l          壓縮時程趕工快速跟併兩種方法,各有利弊,須明辨。

n          Includes Crash and Fast Tracking

n          Crash

l          A schedule compression technique

l          Results in increased cost

n          Fast Tracking

l          A schedule compression technique

l          Phases or activities that normally would be done in sequence are performed in parallel

l          Result in rework and increased risk

 

 Monte Carlo Analysis

l          蒙地卡羅分析是一種模擬分析技術,亦可分析風險。

n          A technique of simulation

n          A distribution of possible activity durations is defined for each schedule activity

n          Calculates a distribution of possible outcomes for the total project

n          Gets an indication of the risk involved in the project

 

Resource Leveling

l          資源撫平是考慮資源的限制及有效利用對要徑法產出的時程所作的調整

n          Also called resource based method

n          Applied to a schedule model that has already been analyzed by the critical path method

n          Keeps selected resource usage at a constant level during specific time periods

n          Results in a longer schedule

n          Resource reallocation from non-critical to critical activities to bring the project back on track

n          Produces a resource-limited schedule, some timed called resource-constrained schedule

 

 Critical Chain Method

l          關鍵鏈是 Eliyahu M. Goldratt 所提出的時程規劃方法,也是其所著企管小說的書名。

n          Modifies the project schedule to account for limited resource

n          Uses non-conservative estimates for activity durations

n          Adds duration buffers that are non-work schedule activities

n          Focuses on managing the buffer activity durations and the resources applied to planned schedule activities

 

Project Schedule

l          專案時程可用三種述圖表來表現, 應視其需要來選用。

n          Formats include

l          Project Schedule Network Diagrams: To show interdependencies between tasks

l          Bar Charts (Gantt Chart): To track progress, report to the team

l          Milestone Charts: To report to senior management; there is no duration of a milestone

 


 

Schedule Control

l          專案進度的量測、 變異的分析、時程的掌控、變更的管制。

n          Controls changes to the project schedule

n          Monitoring & Controlling Process Group

 

 

 

 

 

回首頁